Lafarge Africa PLC – Ewekoro (Nigeria), 2018

ASH600B – SOLID FUEL CONVERSION PROJECT – PHASE 0

Turnkey project

Complete engineering (process/mechanical, civil and structural, electrical and automation)
Supply of mechanical equipment and plate works, structural steel, cladding, doors and windows, electrical and automation
Civil works execution
Erection: mechanical, electrical &
automation equipment
Erection of steel structures
Supervison of commissioning

Quantities:  

  • Mechanical equipment: 120 to.
  • Steel structures: 84 to.

Erection Schedule:

  • Oct. 2017 – Jan. 2018

Commissioning:   Jan 2018