Primary crushing system upgrading – 2012

Client: NCC Roads Norway, Vikan Kross Och      Asfalt Ab (Skanska Group)

Site Location: Skien, Telemark region (Norway)

General Contractor: Sandvik Mining & Construction

Erection: IMSAT SA

Commissioning assistance: IMSAT SA

Erection time: 15 days

Commissioning and tests: 3 days

Scope of work:

  • Old material conveying system dismantling
  • Old screening system dismantling
  • Upgrading and repairing the primary jaw crushing system
  • Screening building installation (steel structure & equipment)
  • New conveyors installation (3 pcs.- total length ~55m)
  • Assistance to commissioning and performance tests.