Lafarge Rezina, Rep. of Moldova – 2007-2009

Client: Lafarge

Location: Rezina, Republic of Moldova

Timeline: Feb ‘07 – March ‘09

Scope of works:

Kiln automation: Engineering, Supply, equipment delivery, commissioning

New coal mill and new elevator for kiln feed

 

  • Engineering: civil works, concrete, steel structure, architecture and partial technology
  • Construction: civil works, steel structures erection
  • Mechanical equipment erection
  • Assistance for commissioning
  • Medium voltage and low voltage distribution: design, MCC & panels supply, erection, commissioning
  • Instrumentation
  • Process control,
  • Software application
  • Lighting

Quantities:

Description Qty.
Fabrication and supply  
Steel structures 647 t
Architecture – Cladding and Accessories 4,749 m2
Civil works  
Excavation 6,011 m3
Concrete 1,916 m3
Reinforcement & anchor bolts 174 t
Formwork 3,827 m2
Backfilling 4,849 m3
Mechanical erection  
Steel structures 647 t
Imported equipment – CBMI (China) 608 t
Architecture – Cladding & Accessories 4,749 m3