Lafarge Lichtenburg, South Africa – 2005-2007

Phase 1: Roller Press modification of existing workshop

Phase 2 & 3: Cement mill 1 and 2 (modifications for existing workshop capacity increase and using of slag)

Scope of works:

  • Engineering (general arrangement drawings, mechanical, civil works, architecture, steel structure, flow sheets, electrical)
  • Civil works
  • Structural steel supply, erection
  • Mechanical equipment supply
  • Mechanical equipment erection
  • Supervision and commissioning

Quantities:

Phase 1:

  • civil works / demolishing: 90 m3
  • steel structure supply: 150,5 t
  • steel structure erection: 152 t
  • mechanical equipment supply (including process ducts & chutes): 30 t
  • mechanical equipment erection: 103 t
  • cladding / insulation: 370 m2
  • demolishing: 108 t

Phases 2&3:

  • civil works / demolishing: 60 m3
  • steel structure supply: 204 t
  • steel structure erection: 432 t
  • mechanical equipment supply (including process ducts & chutes): 220 t
  • mechanical equipment erection: 850 t
  • cladding / insulation: 2200 m2
  • demolishing: 840 t