JPMC, Jordan – Revamping 2 lines for DAP ( Diammonium Phosphate) manufacturing – 2010-2011

Beneficiary:Jordan Phosphate Mines Co.

Client: SNC Lavalin

Project Objective:

  • To increase production capacity from 1250 to/day to 1650 to/day for each Line 75 & 76
  • To revamp existing Production lines and install new generation equipment
  • To meet the environment requirements

Scope of works:

  • Mechanical: Steel structure & Equipment erection, Piping supply & erection, Insulation
  • Electrical & Instrumentation: Equipment erection, Cables supply & erection

Time schedule:

  • Line 75 = June 2010 – January 2011
  • Line 76 = August 2010 – June 2011