Lime kiln reburning line installation – 2013

Client:  Horizon Pulp & Paper

Site Location: Kehra, Harjumaa region, Estonia

Technology Provider: FL Smidth

Mechanical Erection: IMSAT SA

Commissioning assistance: IMSAT SA + FL Smidth

Erection period: 15 July – 28 December 2013

Commissioning and tests: 2 weeks, February 2014

Scope of work:

  • Rotating Kiln preassembly and erection: ID 2,7 m, length 51,3 m
  • Burner Equipment, Kiln Camera System & Gas Analysis System installing
  • Kiln feeding erection: equipment, chutes, ducts
  • Burned Lime Handling installing: Chain conveyors, bucket elevator, slide gates, silos
  • Flue gas cleaning system: Electrostatic Precipitator, Exhaust fan, connection ducts to kiln, ESP, chimney
  • Assistance in commissioning and performance tests.
  • Total weight preassembly and erected: 365,0 Tons