HOLCIM Romania – Campulung Plant – Relocation of the Cement Mill no.4 from Stramberk (Czech Rep.) to Campulung – 2007-2008

 

Owner: HOLCIM Romania – Campulung Plant

Supplier : IMSAT SA

Object: Relocation of the Cement Mill no. 4 from Stramberk (Czech Republic) to Campulung Plant

Scope of works:

  • Dismantling of the Cement Mill (cutting of the Mill) and other equipment
  • Transport of the equipment from Stramberg to Bucharest / Campulung
  • Modification of the Mill geometry (Bucharest) & Equipment refurbishing
  • Transport of the Mill from Bucharest to Campulung
  • Erection of the Cement Mill and other equipment
  • Assistance during Commissioning

 

Time schedule:

Dec 2007 – Aug 2008

  • Dismantling Works (Stramberk) – 01-23Dec. ‘07 & 05-12Jan.’08
  • Transport to Romania – 13Jan – 06Mar ‘08
  • Modification of the Ball Mill – 15Mar – 12May ‘08
  • Mechanical Erection – 14May – Aug ‘08